Bridge building over Triyuga in limbo

Bridge construction over Triyuga in limbo

UDAYAPUR, NOVEMBER 23

The under-construction bridge over the Triyuga River is but to be accomplished on account of inordinate delay and negligence on the a part of contractors.

The development work has not gained momentum although the deadline was prolonged for the sixth time. The contractor has not reached the workplace ever for the reason that quantity was launched in June-July.

Again in 2010, Chaudandi Municipality-based Mahalaxmi Lokpriya JV had signed the contract to finish building work inside three years. However the bridge has been left in a lurch.

The then website in-charge Pradip Chaudhary mentioned issues occurred as the development firm didn’t take the matter severely although the deadline was prolonged again and again.

Diktel Street Mission mentioned the mission price would enhance on account of delay in building work.

DE Gopal Khakurel of the street mission mentioned building of the bridge must be accomplished inside 4 months.

“The contract gained’t be prolonged this time,” he added.

Khakurel mentioned 80 per cent work was accomplished. He added that building of the bridge can be accomplished inside 4 to 5 months if work was expedited.


A model of this text seems in print on November 24, 2020 of The Himalayan Occasions.